So far 15 projects valued at RM34 million have been approved for implementation under the SDC. These projects have all gone through the State’s tender process and the winning tenders were selected based on, inter alia, cost, company track record, competence and delivery schedule.

These projects fall under Phase 1 of the SDC implementation which focuses on plugging gaps in the State’s infrastructure amongst other things. In particular, these projects are aimed at:

• Strengthening Sabah’s agriculture infrastructure;
• Establishing focus on key growth and high-value sub-sectors;
• Empowering rural entrepreneurship; and
• Encouraging participation of SMEs in agri-business.

The details of the tendered projects are shown as follows:

Bil Nama Projek
Lokasi
Anggaran Kos oleh JKR (RM)
Senarai Penender & Pemilik

1.

Pembinaan Jalan ke Ladang Pusat Pembiakan Kambing,Lahad Datu (SDC)

Lahad Datu

278,820.00

 

1.Kekal Gemilang 2 Enterprise
(Martin Bin Dualis)
Kos: RM 275,399.00 *

2.Tegap Sahaya Enterprise
(Abdul Kusen Hussen @ Mujahirin)
Kos: RM 309,262.00

2.

Pembinaan Jalan ke Stesen Penyelidikan Pertanian Bukit Quoin,Tawau (SDC)
Kos:
Kos akan dirunding oleh JKR selaras dengan anggaran JKR.
Tender dipanggil semula jika tidak dipersetujui
.

Tawau

882,300.00

1.Jad Enterprise
(Jalir bin Dan)
Kos: RM 1,035,453,90*

2.Potensi Jati Enterprise
(Sh Suhor Bin Sh Ading)
Kos: RM 1,187,896,00

3.Tetap Perkasa Sdn Bhd
(Perkasa Realty Sdn Bhd Yusuf Bin
Siangah @ Kassim & Justin @ Justine
Paujik)
Kos: RM 1,197,547,00

3.

Pembinaan Jalan ke Stesen pembiakan Ternakan, Tawau (SDC)

Tawau

702,450,00

1.Pembinaan Sinar Jaya
  (Sulaiman Bin Kadusan)
  Kos: RM 665,283.00*

2.Salmang yakin Sdn Bhd
   (Mangkasar bin Mamangku & Laja
   Basal bin Mamangku)
   Kos: RM 689,913.00

3.Saroha Enterprise
   (Haji Maltras Siahaan)
   Kos: RM 694,410.00

4.Syarikat Benamewah
   (Lam Buah Zack)
   Kos: RM 724,896.54

5.Usaha Bumijaya Sdn Bhd
   (Murshid bin Masi & Suhaimi
   Manjun)
   Kos: RM 789,102,80

4.

Pembinaan Jalan Kg. Bokok Kituan ke Kg. Ramayah, Penampang (SDC)

Penampang

2,547,000.00

1. Sasa Bersatu Sdn Bhd
   (Jason Joenoi & Joseph Joenoi)
   Kos: RM 2,695,420.00*

2.Jasa Aktif Sdn Bhd
   (Mohd Faizal bin Mohd Shakir,Teo
   She Tiong & Fatimah shara Ahmad
   Noor)
   Kos: RM 2,713,090.00

3.Manantangan Enterprise
   (Francis Tunding)
   Kos: RM 3,032,270.00

5.

Pembinaan Jalan ke ladang Ternakan Bongawan papar (SDC)

Papar

1,146,000.00

1.Mogindapu Tokou Enterprise
   (Jon Wine Bin Sundang)
   Kos: RM 1,012,000.00*

2. Potensi Jati Enterprise
   (Sh Suhor Bin Sh Ading)
   Kos: RM 1,050,000.00

3.Kontraktor Indah Berkat
   (Rosliza A Hussein)
   Kos: RM 1,113,890.00

4.Radiant Suria
   (Farah @ Ayang binti Jalumin)
   Kos: RM 1,120,140.00

5.Maxit Corporation Sdn Bhd
   (Wong Lee Yeh & Tam Kok Wing)
   Kos: RM 1,135,305.00

6.Subur (S) Enterprise
   (Justin Bin Tianji & Mickley bin
   Mintik)
   Kos: RM 1,140,870.00

7.Tetap Perkasa Sdn Bhd
   (Yuson Bin Siangah @ Kassim &
   Justine Paujik)
   Kos: RM1,580,173.00

6.

Pembinaan Jalan ke Pusat Pembiakan Kambing, Bongawan, Papar (SDC)

Papar

1,116,000.00

1. Potensi Jati Enterprise
   (Sh Suhor Bin Sh Ading)
   Kos: RM 1,000,000.00 *

2. Mogindapu Tokou Enterprise
   (Jon Wine Bin Sundang)
   Kos: RM 1,056,000.00

3.Kontraktor Indah Berkat
   (Rosliza A Hussein)
   Kos: RM 1,067,770.00

4. Radiant Suria
   (Farah @ Ayang binti Jalumin)
   Kos: RM 1,113,890.00

5. Maxit Corporation Sdn Bhd
   (Wong Lee Yeh & Tam Kok Wing)
   Kos: RM 1,145,025.00

6. Subur (S) Enterprise
   (Justin Bin Tianji & Mickley bin
   Mintik)
   Kos: RM 1,149,900.00

7. Tetap Perkasa Sdn Bhd
   (Yuson Bin Siangah @ Kassim &
   Justine Paujik)
   Kos: RM 1,576,370.00

7.

Pembinaan Jalan ke Stesen Perikanan, Babagon, Penampang (SDC)

Penampang

593,000.00

1.Sri Annu Enterprise
   (Yatiah Bte Sulaiman @ Sariah)
   Kos: RM 364,725.00

2.Seri Sosopon Enterprise
   (Johnny Gantasim)
   Kos: RM 470,256.00

3.Gemilang Enterprise
   (Pekit Bin Laini)
   Kos: RM 504,192.00*

4.Pembinaan Sinar Jaya
   (sulaiman Bin Kabusan)
   Kos: RM 544,954.00

5.Saroha Enterprise
   (Maltras Siahaan)
   Kos: RM 579,970.00

6.KAT Enterprise
   (Guntis Bin Guring)
   Kos RM 579,970.00

7. Saroha Enterprise
   (Maltras Siahaan)
   Kos: RM 586,053.30

8.Usaha Bumiwaja Sdn Bhd
   (Pekit Bin Laini)
   Kos: RM 595,498.00

9.Majupena Enterprise
   (Victor Moosom @ Jikomin)
   Kos: RM 566,453.00

10. Subur (S) Enterprise
    (Justin Bin Tianji & Mickley bin
    Mintik)
    Kos: RM 800,830.00

11.Sosopon Jaya Enterprise
    (Rugan Bin Manjin)
    Kos: RM 1,127,000.00

8.

Pembinaan Jalan ke Pusat Pembiakan Ternakan Timbang Menggaris, Kota Belud (SDC)

Kota Belud

1,183,000.00

1. Kontraktor Indah Berkat
   (Rosliza A Hussein)
   Kos: RM 1,040,554.40*

2. Mogindapu Tokou Enterprise
   (Jon Wine Bin Sundang)
   Kos: RM 1,056,000.00

3. Potensi Jati Enterprise
   (Sh Suhor Bin Sh Ading)
   Kos: RM 1,100,000.00

4.Pemborong Ampagong
   (Abu Samat Bin Eling)
   Kos: RM 1,157,700.00

5.Sembilan Jaya Co
   (Abdul Nain Bin Norsidek)
   Kos:RM 1,160,000.00
6. Subur (S) Enterprise
    (Justin Bin Tianji & Mickley bin
    Mintik)
   Kos: RM 1,214,500.00

7.Sri Unik 2020 Tetap Perkasa Sdn Bhd
   (Yusof Bin Siangah @ Justine Paujik)
   Kos: RM 1,345,641.00

9.

Pembinaan Jalan ke Stesen Mekanisasi Padi Binaong, Keningau (SDC)

Keningau

1,5100,000.00

1.Magong Enterprise
   (Manuel Gongkung)
   Kos: RM 1,520,315.00*

2.Jad Enterprise
   (Jalir Bin Dan)
   Kos: RM 1,520,332.50

3.Syarikat Putera Projek
   (Yasin @ Archad Bin Diasan)
   Kos: RM 1,558,926.00

4.Syarikat Serbena Construction
   (Joseph Amin)
   Kos: RM 1,610,048.75

10.

Pembinaan Jalan Ansip Farm Ferry, Keningau (stesen Pembiakan Ternakan Sebrang) (SDC)

Keningau

5,073,500.00

1.DHT Holdings Sdn Bhd
   (Ahmad Shah Tambakau)
   Kos: RM 4,818,734.50*

2.Ahmad J.S Construction Sdn Bhd
   (Shahczarena Bte Abdullah)
   Kos: RM 6,277,255.80

11

Pembinaan Jalan ke Pusat Pembiakan Ternakan Wario, Kota Belud (SDC)

Kota Belud

1,250,000.00

1. Kontraktor Indah Berkat 
(Rosliza A Hussein)
Kos:RM1,049,941.80

2. Mogindapu Tokou Enterprise
(Jon Wine Bin Sundang)
Kos:RM1,099,356.20

3. Pemborong Ampagong
(Abu Samat bin Eling)
Kos:RM1,143,300.30 *

4. Sembilan Jaya Co.
(Abdul Nain bin Norsidek)
Kos:RM1,150,000.30
Potensi Jati Enterprise
(Sh Suhor Sh Ading)
Kos:RM1,150,500,00

5. EAJ Construction
(Anthony Yaga)
Kos:RM1,413,897.10

6. Tetap Perkasa Sdn. Bhd.
(Yusof bin Siangah @ Kassim & Justin @ Justine Paujik)
Kos:RM1,665,601.00

7. Subur (S) Enterprise
(Justin bin Tianji & Mickiey bin Mintik)
Kos:RM2,291,000.00

12

Pembinaan Jalan ke Projek SAS (Small Holder Assisted Scheme) di Kg. Galiun, Pitas (SDC)

Pitas

5,513,000.00

1. Ahmad JS Construction Sdn Bhd
(Ahmad Jasad bin Salali)
Kos:RM5,090,135.00

2. Bagus Guna Sdn Bhd
(Aladin bin Siau & Masitah binti Hasim)
Kos:RM5,300,710.00

3. March Merit Sdn Bhd
(Lo Soon Foh & Tan Yu Ling)
Kos:RM5,381,180.00 *

4. Rimas Enterprise
(Ali Daimi bin Basni @ Ali Zaini)
Kos:RM5,991,443.60

5. Pembangunan Sulaiman Group Sdn Bhd
(Hj Sulaiman bin Mohd Abdullah & Akob bin Sirin)
Kos:RM6,657,908.00

6.Asang Komunta Kontraktor
(Yosang bin Komonta)
Kos:RM8,999,198.80

13.

Pembinaan Jalan Ternakan Sinarut, Ranau (SDC)

Ranau

2,047,000.00

1. Mogindopu Tokou Enterprise
(Jon Wine bin Sundang)
Kos:RM1,750,000.00

2. Syarikat Siniah
(Amisah Gonsoi)
Kos:RM1,855,976.00 *

3. Tetap Perkasa Sdn Bhd
(Perkasa Realty Sdn Bhd, Jusoh bin Siangah
@ Kassim & Justin @ Justine Paujik)
Kos:RM1,985,000.00

14.

Pembinaan Jalan Taman Kekal Pengeluaran Makanan (TKPM), Nabawan, Pensiangan (SDC)

Nabawan, Pensiangan, Lahad Datu

6,541,500.00

1. Ahmad JS Construction Sdn Bhd
(Ahmad Jasad bin Salali & Nelmond bin None @ Paulus)
Kos:RM6,121,660.00 *

2. DHT Holdings
(Ahmad Shah Tambakau & Shahczarena bte Abdullah)
Kos:RM6,233,424.94

15.

Pembinaan Jalan Kiulu Longkou Lama, Tuaran (SDC)

Tuaran

6,456,000.00

1. Pembangunan Asli Sdn Bhd
(Joseph Linggian @ Joseph Chong, Yap Mui Len
@ Helen @ Donysius Jinih) Kos:RM5,416,160.00

2. Bagus Guna Sdn Bhd
(Aladin bin Siau & Masitah binti Hashim)
Kos:RM5,849,627.00

3.Asang Komunta Kontraktor
(Yosang bin Komonta)
Kos:RM5,878,137.00 *

4. March Merit Sdn Bhd
(Lo Soon Foh & Tan Yu Ling)
Kos:RM5,930,360.00

5. Pembangunan Sulaiman Group Sdn Bhd
(Hj Sulaiman bin Mohd Abdullah bin Sirin)
Kos:RM7,401,538.00